The INTUIT DOME/CLIPPERS ARENA will start having calls from SUMMIT SWING to install the LED OCULUS. ZELLER ELECTRIC will be installing all the power for the LED OCULUS and will need manpower as well.  

ELAC SOUTH GATE EDUCATIONAL CENTER is a large LAUSD project that TAFT ELECTRIC is performing the electrical power for. It’s a ground-up $98 million project that also has BAKER ELECTRIC doing controls and FIRST FIRE installing low voltage and fire alarms. 

SASCO ELCTRIC has two high-rises in DOWNTOWN L.A. called the Weingart Tower and Olympic/Hill Street Tower. Both are in their early stages and will need manpower in the immediate future.  

Keep an eye out for more information on the LA CONVENTION CENTER REMODEL. 