District 1 North Report — September 2022

District 1 North Report — September 2022

September 28, 2022
Greetings from District One North. I hope this report finds you and your families well. A…
District 1 South Report — September 2022

District 1 South Report — September 2022

September 28, 2022
Intuit Dome/Clippers Arena – The steel for the project is moving at a good pace which…
District 1 South Report — August 2022

District 1 South Report — August 2022

August 25, 2022
Jefferson High School is a $163 million project that has been awarded to ILB Electric and…
District 1 North Report — August 2022

District 1 North Report — August 2022

August 25, 2022
Brothers and Sisters Greetings from District One North.  I hope this report finds you and
District 1 South Report — July 2022

District 1 South Report — July 2022

July 26, 2022
Intuit Dome/Clippers Arena – SASCO Electric is doing the single line portion of the project and…
District 1 North Report — July 2022

District 1 North Report — July 2022

July 26, 2022
Brothers and Sisters Greetings from District One North. I hope this report finds you and your…
District 1 South Report — June 2022

District 1 South Report — June 2022

June 28, 2022
Intuit Dome/Clippers Arena – SASCO Electric is doing the single line portion of the project and…
District 1 North Report — June 2022

District 1 North Report — June 2022

June 28, 2022
Greetings from District One North., Brothers and Sisters. I hope this report finds you and your…
District 1 South Report — May 2022

District 1 South Report — May 2022

May 9, 2022
The 8th and Figueroa high rise is being worked by Rosendin Electric. They will be needing…